Which building category is yours?

The Building Act 2055 classifies buildings into four categories, A to D. Category C covers smaller residential buildings and Category D small houses of local materials. The exact thresholds for each category are as set in the Act; check them there or with your municipality.

NBC 205:2024, the ready-to-use reinforced-concrete guideline, applies to Category C buildings built under the supervision of sub-engineers. Other buildings need professional engineers.

What EBPS is

EBPS was developed with UNDP/CDRMP and was introduced first in Kathmandu, Lalitpur and Butwal. You submit the application and track it online.

Example EBPS portals

Documents you typically need

Documents typically include the following. Your municipality's own list is the one that counts.

  • Land ownership certificate (lalpurja)
  • Citizenship certificate
  • Land tax receipt
  • Plot map and neighbouring plots (char killa)
  • Building drawings
  • NBC design data

The stages

The process commonly runs in these stages:

  • Temporary permit to build up to the plinth
  • Plinth inspection
  • Permit to build above the plinth
  • Completion certificate

In Kathmandu Metropolitan City (KMC), the system sends SMS updates at each stage.

Fees, timelines and who signs the drawings

Fees, timelines and who signs the drawings are set by each municipality. Check its EBPS portal.