Roads, Bridges & Buildings

Page 4 of 4
  1. Roads, Bridges & Buildings

    A tourist cruise boat of roughly 60 tonnes, carried off by the flooded Narayani, has jammed against a pier of the Narayani Bridge at Gaindakot.

    Chitwan road engineers plan to cut it into sections and lift it out with three cranes, and heavy vehicles have been kept off the bridge while its safety is checked.

    Summary written by the Engineer Nepal desk

    Read at The Himalayan Times
    The Himalayan Times ·
  2. Roads, Bridges & Buildings

    A preliminary tally by the physical infrastructure ministry lists heavy flood damage since 25 September: washed-out bridge approaches on the Kaligandaki Corridor, a lost concrete bridge, collapsed stretches of the Dumre–Besisahar–Chame road, several damaged suspension bridges and 31 drinking water schemes.

    Work to reopen roads began on Sunday.

    Summary written by the Engineer Nepal desk

    Read at Onlinekhabar English
    Onlinekhabar English ·
  3. Roads, Bridges & Buildings

    Flooding in the Champamati stream set off a landslide in Suryabinayak-8, Bhaktapur, that has reached house yards and exposed at least one building's foundation, with four more homes at risk.

    The ward chair says the municipality cannot fund slope control alone and will seek federal and provincial money.

    Summary written by the Engineer Nepal desk

    Read at The Kathmandu Post
    The Kathmandu Post ·
  4. Roads, Bridges & Buildings

    The Kaligandaki flooded Farse settlement in Parbat's Jaljala Rural Municipality, sweeping away around 80 houses, while a landslide in Palpa killed one person.

    Security forces moved residents and their belongings to safety; power and phone links in the area were down and a full damage assessment was still under way.

    Summary written by the Engineer Nepal desk

    Read at The Kathmandu Post
    The Kathmandu Post ·
  5. Roads, Bridges & Buildings

    The Siddhababa Tunnel on the Butwal–Palpa road is being readied for traffic by mid-November, though the project chief now cites 1 December after flood-related delays in material deliveries.

    Lining, paving and other civil works are finished, electromechanical work remains, and physical progress is close to 70 per cent.

    Summary written by the Engineer Nepal desk

    Read at Onlinekhabar English
    Onlinekhabar English ·
  6. Roads, Bridges & Buildings

    The Department of Roads aims to reopen the flood-damaged Galchhi–Syaphrubesi road by mid-October.

    Most sections are passable after repairs and an army-built Bailey bridge at Devighat, but through traffic to Syaphrubesi must wait for two more Bailey bridges, including a 72-metre span at Betrabati in Rasuwa.

    Summary written by the Engineer Nepal desk

    Read at The Rising Nepal
    The Rising Nepal ·
  7. Roads, Bridges & Buildings

    The Department of Roads is studying two permanent fixes for the landslide-prone Krishnabhir stretch of the Prithvi Highway: a tunnel through the slope or a viaduct further along.

    A technical report is due in about two months, after which tendering will start; a temporary track now bypasses the damaged section.

    Summary written by the Engineer Nepal desk

    Read at Onlinekhabar English
    Onlinekhabar English ·